Pile Head Water Insulation
After the Bored Pile concrete is laid, the field lean concrete is laid with machine finishing. Bored pile heads are filled with grout mortar with the help of a pulley and smoothed. A chamfer is made between the surface where grout mortar is applied and the lean concrete. Then, Technobit is applied by free laying on the lean concrete and full bonding on the pile heads. Technobit should be wrapped up to the column sprouts. After the insulation application, geotextile felt and protection concrete are laid on it.